November 5, 2003
Joint meeting of the Smyth County Board of Supervisors.
The county's documents
- Minutes (476 pages)
Summary
Written by software from the documents above. It can be wrong or leave things out. Quote the minutes, not this.
The Smyth County Board of Supervisors and Town of Saltville Council held a joint meeting on November 5, 2003, at Saltville Town Hall. Chip Worley and Lance Morgan from Anderson & Associates presented an overview of the Allison Gap Sewer Project. Bids received in April 2003 for three divisions resulted in a construction fund shortfall of $2,142,325.00. Anderson & Associates was authorized to restructure and rebid the project to secure additional funds and reduce the shortfall. The current estimated shortfall is $1,773,725.00, which must be resolved before Rural Development allows the firm to proceed with rebidding. The presented shortfall summary included a low bid difference of -$2,142,325, offset by $100,000 from the Saltville RD Loan, $100,000 from Plumbing Funds (CDBG), $218,443 from Re-Design, -$349,843 in Related Costs, $100,000 from SE/RCAP, and $200,000 from CDBG, totaling -$1,773,725. Several scenarios for obtaining funding and commitment responsibilities were discussed.
- Anderson & Associates authorized to restructure and rebid the Allison Gap Sewer Project
- Initial construction fund shortfall identified at $2,142,325.00
- Current project shortfall estimate reduced to $1,773,725.00
- Rural Development requires shortfall resolution before allowing rebidding
- Funding sources include Saltville RD Loan, CDBG, and SE/RCAP
- Related costs of -$349,843 included in the shortfall calculation